Thank you very much for purchasing "Electric Heating Brick " the world first modular Electric Heating Concrete Panel. This product is designed and manufactured by Duralogic limited, this instruction will cover model : EHB3k02-01;its installation !

THIS EQUIPMENT SHALL BE INSTALLED ONLY BY QUALIFIED PERSONNEL WHO ARE FAMILIAR WITH THE CONTSTUCTION AND OPERATION OF THE APPARATUS AND THE RISK INVOLVED

THE INSTALLATION OF THIS HEATING PRODUCT SHALL BE IN ACCORDANCE WITH THE MANUFACTURER'S INSTRUCTIONS AND THE REGULATIONS OF THE AUTHORITY OF JURDSDICTION.

You could install this product into two different

Before install this product, several things need to prepare first, leveling the floor

กก

 
This product is mainly designed for heating floor purpose,
1
check all the accessory included ; should include power connection cable ; three wire, PLR02 RED, PLB02;BLUE and PLG02; GREEN all 18AWG wire, and IB01 inter-brick connection YELLOW, 22AWG 
wire .you also need to prepare the tools, 5”Mini Bent Nose Pliers, and silicon sealant if you want to fix  
the heating brick to wooden slab beneath , then prepare the screw (4mm * 22mm) , and screw driver !
 
2
measure the dimension of space you like to install, calculate how many rows and columns
of EHB will be installed, then follow the connection routing map we provide !
 
3
This product  EHB3k02-01 is designed to be installed in two pieces EHB series connected,
then connected with 120VAC power source parallel   !
 
   Warning :  
  Each wire can only operate at Maximum 1200watts, this mean one continuous connection wire only can connect 74 piece of EHB, no more than this quantity ! then this wire need to connect with 120VAC power source ,because 18AWG wire can only support this power consumption safely . you need another continuous wire to connect another set of 74 pieces of EHCB.  

fixing the nail into holes in each corner !

Warning :
You have to use the tool; 5"Mini Bent Nose Pliers to plug and unplug
 the in-line connector, Do not pull by hand, it willdamage the wire !

Tool, 5" Mini bent nose Pliers insert the wire    

Unplug the wire

1 Now, you can arrange EHB by the way our connection routing map suggested ! then  you can fix EHB to sub-floor; no matter it is concrete or wood, by snap nail into four holes in each corner.
2 Check carefully , see the direction of EHB connector is the same as our routing map suggest ! Because our in-line connector is spaced at fixed distance, follow our suggestion of EHB arrangement will make EHB connection as one continuous wire ! Note: sometimes you might need to scarify one or two EHB without connecting ! if the shape of space you wish to install is very in-regular !
3 Connect the wire , place the wire ,and insert into the conduit slot to fix it, push the connector as much as possible into EHB , see the drawing of connector and connection !
4 after you connect the connector , you have to apply the silicon glue fully into the section of  connector, there are three sections of connector for each EHCB connection conduit ! and silicon glue will prevent water and humidity to affect connector.
5 the rest of conduit; will be poured filled with concrete cement fully.
6 After each row installed , you should check the resistance always, make sure it is OK, then install next line of EHB ! repeat the procedure from d) to I) !